Is it possible to show the secondary and/or tertiary critical path in Microsoft Project? The view menu has a way to filter to only those tasks without slack (i.e. the critical path), but is there a way to show more critical paths without artificially shortening something in the real critical path?
Edit:
To Clarify based on the answers below, just increasing the slack threshold at which something is considered the critical path is not at all what I'm after for a couple of reasons.
- The secondary or tertiary critical path has some arbitrary amount of float to the primary critical path. So just changing this threshold would require tedious guess and check and could change whenever the schedule logic or status is updated.
- Changing this threshold would cause all three paths to be considered "the" critical path, with no obvious visual means of distinguishing them from each other.