I need an advice and it's about the best option to choose in an agile project, here is the situation :
- A sprint backlog contains between 15 and 20 user stories
- A the last day of the sprint, we understand that we will not finish 1 story, we did some code on it, and we will need to continue in the next sprint
- This US was estimated initially at 13 points, and the developer says that he did 50% of the US
What to do, should we create a new ticket in the next sprint, exactelly the same US, re-estimate it to maybe 5 points because we did some job on it ? and closing the one we started after re-estimating it to 8 points ?
Or to keep same 13 points in the next sprint to this same task ?