I have added a work resource entry "Laborers" with Max. Units 10000% in the Resource Sheet. The resource calendar for this resource is standard and all the units are available.
Now I want the work of Activity A (350h during 30 working days) is distributed equally between three general laborers from resource "Laborers". Show me the way resource definition and assignment should be for this purpose using Microsoft Project 2013.