We are starting a Sprint today, first day of a 3-week Sprint. Our requirements from the client are still evolving, so remaining hours are estimated on some unclear values.
How should a deviation in overall design be managed in Scrum? For example, a requirement covered in this Sprint changes drastically, causing the Sprint to land up days behind schedule. Are we still committed to all the work, or do Sprint items get moved out to accommodate the change?