Search Results
Search type | Search syntax |
---|---|
Tags | [tag] |
Exact | "words here" |
Author |
user:1234 user:me (yours) |
Score |
score:3 (3+) score:0 (none) |
Answers |
answers:3 (3+) answers:0 (none) isaccepted:yes hasaccepted:no inquestion:1234 |
Views | views:250 |
Code | code:"if (foo != bar)" |
Sections |
title:apples body:"apples oranges" |
URL | url:"*.example.com" |
Saves | in:saves |
Status |
closed:yes duplicate:no migrated:no wiki:no |
Types |
is:question is:answer |
Exclude |
-[tag] -apples |
For more details on advanced search visit our help page |
4
votes
How to manage risk of "just in time" delivery?
There are two ways to do this:
Either taking a Critical Chain approach and have a bucket of buffer for the whole schedule (this would be my recommended approach), or, for a more quick and dirty approach …
1
vote
MS Project with Sub-Projects
Check that the header tasks (of which these are sub-tasks) are set to calculate percent complete based on sub-tasks/
Is the schedule mode auto or manual? …
1
vote
Project schedule reviews
For a high level review I would compare the amount of uncertainty against the amount of "buffer" in the schedule. … This relies heavily on experience and a general feel for the range of what could go wrong and a feel for stakeholder tolerance/parameters to accept change in the schedule, scope, cost... …