Skip to main content
Improved readability and added missing tag
Source Link

MS Project seems to take a task and calculate Per Day Workper day work by dividing Total Worktotal work by Durationduration. 

In the schedule I am working on, each resource is available for 10 hours per day, but projectMS Project doesn't take advantage of this. 

I would like to level my schedule based on the 10 available hours per day rather than simply spreading my tasks out beyond the predetermined Finishfinish date. I can do this manually by moving Workwork around in the Resource Usage tab, but I was wondering if there is a simpler way to do this. Thanks.

Hopefully a useful visual   

(Also, this is my first time using Project Management Exchange, so if my etiquette is not up to par please feel free to direct me to any guidelines that would improve my question.)

Project seems to take a task and calculate Per Day Work by dividing Total Work by Duration. In the schedule I am working on, each resource is available for 10 hours per day, but project doesn't take advantage of this. I would like to level my schedule based on the 10 available hours per day rather than simply spreading my tasks out beyond the predetermined Finish date. I can do this manually by moving Work around in the Resource Usage tab, but I was wondering if there is a simpler way to do this. Thanks.

Hopefully a useful visual  (Also, this is my first time using Project Management Exchange, so if my etiquette is not up to par please feel free to direct me to any guidelines that would improve my question.)

MS Project seems to take a task and calculate per day work by dividing total work by duration. 

In the schedule I am working on, each resource is available for 10 hours per day, but MS Project doesn't take advantage of this. 

I would like to level my schedule based on the 10 available hours per day rather than simply spreading my tasks out beyond the predetermined finish date. I can do this manually by moving work around in the Resource Usage tab, but I was wondering if there is a simpler way to do this. Thanks.

Hopefully a useful visual 

(Also, this is my first time using Project Management Exchange, so if my etiquette is not up to par please feel free to direct me to any guidelines that would improve my question.)

added image of issue
Source Link

Project seems to take a task and calculate Per Day Work by dividing Total Work by Duration. In the schedule I am working on, each resource is available for 10 hours per day, but project doesn't take advantage of this. I would like to level my schedule based on the 10 available hours per day rather than simply spreading my tasks out beyond the predetermined Finish date. I can do this manually by moving Work around in the Resource Usage tab, but I was wondering if there is a simpler way to do this. Thanks.

Hopefully a useful visual (Also, this is my first time using Project Management Exchange, so if my etiquette is not up to par please feel free to direct me to any guidelines that would improve my question.)

Project seems to take a task and calculate Per Day Work by dividing Total Work by Duration. In the schedule I am working on, each resource is available for 10 hours per day, but project doesn't take advantage of this. I would like to level my schedule based on the 10 available hours per day rather than simply spreading my tasks out beyond the predetermined Finish date. I can do this manually by moving Work around in the Resource Usage tab, but I was wondering if there is a simpler way to do this. Thanks. (Also, this is my first time using Project Management Exchange, so if my etiquette is not up to par please feel free to direct me to any guidelines that would improve my question.)

Project seems to take a task and calculate Per Day Work by dividing Total Work by Duration. In the schedule I am working on, each resource is available for 10 hours per day, but project doesn't take advantage of this. I would like to level my schedule based on the 10 available hours per day rather than simply spreading my tasks out beyond the predetermined Finish date. I can do this manually by moving Work around in the Resource Usage tab, but I was wondering if there is a simpler way to do this. Thanks.

Hopefully a useful visual (Also, this is my first time using Project Management Exchange, so if my etiquette is not up to par please feel free to direct me to any guidelines that would improve my question.)

Source Link

MS Project Overallocation

Project seems to take a task and calculate Per Day Work by dividing Total Work by Duration. In the schedule I am working on, each resource is available for 10 hours per day, but project doesn't take advantage of this. I would like to level my schedule based on the 10 available hours per day rather than simply spreading my tasks out beyond the predetermined Finish date. I can do this manually by moving Work around in the Resource Usage tab, but I was wondering if there is a simpler way to do this. Thanks. (Also, this is my first time using Project Management Exchange, so if my etiquette is not up to par please feel free to direct me to any guidelines that would improve my question.)