For the PMBOK 5th Edition.
2 of the Perform Quality Assurance Tools & Techniques are
-Quality Audit
-Process Analysis
( Pgs 438-439, Head First PMP 3rd Edition, Jennifer Greene, PMP & Andrew Stellman, PMP )
"Quality Audits are reviews of your project by your company. They figure out whether or not you are following the company's process."
"Process Analysis is when you look at your process to find out how to make it better. You use your Process Improvement plan to do this one."
( Pgs 438-439, Head First PMP 3rd Edition, Jennifer Greene, PMP & Andrew Stellman, PMP )
( Pgs 408-409 , PMP Project Management Professional Exam Study Guide, Kim Heldman, PMP )
"The purpose of a quality audit.....to identify ineffective and inefficient activities or processes used on the project."
"Process Analysis looks at process improvement from an organizational and technical perspective......
.....process analysis follows the steps in the process improvement plan and examines the following:
-Problems experienced while conducting the project
-Constraints experienced while conducting the work of the project
-Inefficient and Ineffective activities identified during process operation"
( Pgs 408-409 , PMP Project Management Professional Exam Study Guide, Kim Heldman, PMP )
It seems to me that both PMP study guides don't say the same thing.
Could someone please provide definitions for Quality Audit and Process Analysis, and explain the difference between the said two terms?