Let's suppose there's a customer who needs a software product and there's a custom software development company that is ready to implement this product. They agreed that the customer has to pay X (dollars) for the product.

Am I right, that there're two budgets here? The first one is of the buyer - X (dollars). But for the vendor the budget is not equal to X, it is much less than X (at least because the vendor needs to have some profit, so it can't spend all the sum X on implementing the project)?

1
  • 1
    Budgets and sale/purchase prices are related, but are not interchangeable terms.
    – Todd A. Jacobs
    Commented Dec 20, 2020 at 16:49

3 Answers 3

3

Don't confuse budget with price. You set a price, but you build a budget.

A price is usually a number that reflects an amount of money you pay on some product. The price includes the cost of production for that product, eventual taxes (like VAT, for example), and a profit that the company expects to make from selling the product.

A budget is not a simply a number reflecting an amount of money. Although you often hear people say "we have a budget of $200,000 for such and such", that is an oversimplification. If, for example, you want to organize a Pizza Friday at the office, and your manager says you have a budget of $250, then that simply means you can spend $250 on pizza. But within a project management context, a budget means more of a financial plan, than just a simple amount of money. Yes, you can then say the budget for a project is $200,000, but you also need to include "the story" of how you got to that amount. When you read the PMBoK, the focus is on all the process groups and knowledge areas you will need in order to build a budget.

So, for a project, you need to build a budget by figuring out the activities needed to build the software, then estimating that work. You then figure out what people you need and based on the estimation and the hourly rate of your employees, you forecast how much you will need to pay on salaries. Maybe you also need to take into account Christmas bonuses for those people. You need to account for other costs too, like hardware equipment, software licenses, contingency reserves (for when things don't go smoothly), maybe traveling expenses if needed, other professional services (like lawyers for drafting contracts), etc. Adding all these things together will give you an image on what costs will be necessary to build the software, and now you can say an amount like $200,000. Once you have built the budget that tells you what is needed to build the thing, you can now set the price that you will ask for it, a price that also includes the profit. And of course, while you build the software, you have to monitor the costs and see if they match the budget you have built and financed for it, and make necessary adjustments if needed.

If you look at this from both the customer and contractor perspectives, then yes, you can say that there are two budgets:

  • for the contractor building the software: the budget is all the above mentioned things that are needed to build the software. It's the financial plan and its conclusions of what it will cost, to know if you can finance such a project.
  • for the customer buying the software: the budget contains the price they pay for the software, but can also be any extra costs from the above mentioned things. For example, they might pay just for software, so they need to include in their budget any hardware needed to run it. Maybe they have their own people overseeing things at the contractor, so they need to include the salaries in their plans. They might also have expenses with lawyers helping them on their side of the contract negotiations, etc. So the customer too needs to build their own budget, to see how much this project will cost them overall, not just what the custom software they ordered from someone else will cost.
0

A budget is normally more than one number and may include distinct budgets for people, operational expenses and capital costs. You are right that the total budget from the vendor's point of view is normally less than the price you expect the customer pay. There are exceptions. Many vendors will avoid quoting a firm fixed price at all unless they are willing to do a loss leading piece of work, i.e. the work itself doesn't turn a profit but is expected to generate other profitable work in future.

5
  • So there's one project, one contract, but there're two budgets? Right?
    – Daniel
    Commented Dec 20, 2020 at 13:05
  • If the price the customer pays is fixed then I would not describe that price as a "budget" at all. Surely the point of a budget is that you measure expenditure against it but that's pretty meaningless if the price is fixed because there is presumably nothing to measure. You might have a schedule of payments with associated dates or milestones but I would just call that a payment schedule, not a budget.
    – nvogel
    Commented Dec 20, 2020 at 13:40
  • Thank you, but a fixed-price is a very common contract in PMBoK and they use the term budget, so it's unclear what you mean...
    – Daniel
    Commented Dec 20, 2020 at 15:18
  • @Daniel, PMI's PMBOK Guide tries to cover a range of possibilities for different kinds of work in many different industries. It is not a guide on how to run software projects.
    – nvogel
    Commented Dec 21, 2020 at 13:28
  • Thank you, I've got what you meant.
    – Daniel
    Commented Dec 21, 2020 at 18:16
0

No matter if you buy it or build it, you attach your fee before you sell it.

I think there is an issue with lingo. Let me see if this helps:

Seller of services/product: Costs + Fee = Price

Buyer of services/product: Seller's price = buyer's costs The buyer will have in its budget that seller's costs and other costs associated with that project or program. That buyer can also be a seller and will add fee to its costs for a new price to its customer(s).

If the original seller has what you are calling vendors, or really other subcontracted parts of work, that seller becomes a buyer from that vendor or other subcontractors. Those third parties will have their costs + fee to arrive at a price for the original seller. That price becomes cost for that seller who will then add its fee to arrive at a price for its customer.

3
  • Roughly said, a budget for a vendor is its expeditures planned. A budget for the buyer is the expeditures of the vendor plus fee. Right? Every party of a contract has/considers its own budget?
    – Daniel
    Commented Dec 20, 2020 at 16:08
  • @Daniel, the purchaser likely has other things as part of their budget too: infrastructure costs, their internal human resource costs. If they are prudent they may also have some contingency for additional work that isn't deemed to be part of the original scope.
    – nvogel
    Commented Dec 20, 2020 at 17:16
  • Got it, thank you!
    – Daniel
    Commented Dec 20, 2020 at 17:42