0

I don't know if the name of the question is clear what I would like to do is:

I need to adjust the most likely time for an activity of my project in purpose of the probability of any path through the network being completed in x days must not be less than 0.94.

I know how to calculate the probability for a given time and a given path. But I don't know to solve this problem.

1 Answer 1

1

PERT Analysis was discontinued as of MS Project 2010. You can add this functionality back into MS Project; it is not a trivial task though. A detailed, step-by-step explanation of how to do this can be found here: http://blogs.technet.com/b/projectified/archive/2009/11/24/3296207.aspx

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.