I sometimes use Freemind in the early startup process of projects for brainstorming with the project team. With freemind, it is possible to save the mindmap as an ODT file which then creates a WBS for all tasks.
I would like to use this WBS in Microsoft project without having to manually indent tasks as subtasks.
So: instead of marking all created activities i would like to copy/paste or import and get the hierarcy at start - as created from freemind export.
Freemind gives me:
- Activity 1
1.1 Activity 2
1.1 Activity 3
1.1.1 Activity 4
1.2 Activity 5
... and so on.
Is this possible? Does anyone have experience importing pre-made WBS hierarcies for MS Project?
List item
- Are there any alternative scheduling applications that I should look into with this possibility?
Best regards, Pär