0

I run a small business and I have to take on an additional resource to handle an increased workload from one of my clients. How do I calculate my project management fee?

I estimate I will spend about 25% of time on project management. So, do I add 25%? on top of the hourly rate or the total of my rate + resource rate? I've heard varying different methods...

1 Answer 1

2

The cost of managing a project is typically a range of the total cost of the project and is very industry dependent.

For example, your industry may suggest that PM and PM control costs will be 15% to 20% of the total cost of the project. This would suggest that, adding a resource at an assumed 1,800 hours a year, the project would require 270 to 360 hours of PM resources. So you would price the resource for the 1,800 hours and then price some PM resources somewhere between the 270 to 360 hours.

That said, the PM and PM control area is not necessarily linear with the cost of the project. As your project may grow in scope, you do not necessarily need to add the PM resources in an equivalent way.

In your example, it sounds like you are only devoting yourself to the increase of managing an additional resource. If you intend to only decrease your designing time and replacing it with managing time but your overall hours do not increase, then I would suspect you would not "charge" for the PM part of this scope change. Or, if you expect to be consistently working overtime to manage, then you would increase the costs of PM in this change.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.