I would like to see a list of all tasks that satisfy one of the following:
- The task has no predecessors
- Every predecessor that the task has is marked as 100% complete.
I can add simple filters from View > Filter > New Filter, but I can't figure out how to test every predecessor of a task. Is there a way to use some advanced filtering functionality to accomplish this?