1

What if the project manager changes all of a sudden during the project at any phase (Due to resignation / Personal reasons / Accident). Does the Project charter also change with it?

If so, Who does the changes, what is the process/way to do it?

4

Project Charter is a document that formalizes the existence of a project and gives authority to the project manager to use organizational resources for the completion of that project.

Having said that, a change of project manager should not have any impact on the Project Charter. The only change would be to update the assigned project manager's name in the document. This would be done by the new project manager with the approval of current project sponsor.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.