1

I am using TaskJuggler to manage a project. In my particular project, we are doing basic research, so some tasks are not guaranteed to be completed, due to large numbers of unknowns. I would like some way to denote that "we worked on this task, but this task is permanently incomplete because it is not complete-able".

In my limited experience, TaskJuggler easily handles the task states of "incomplete" and "complete". Is there a way to denote other options outside of these two possibilities, such as a "failed" state?

2 Answers 2

1

Split your research tasks into two parts

I am not familiar with TaskJuggler. However, I would recommend that you split your research tasks into two parts:

  1. Ascertain task feasibility.
  2. Work the task to completion.

You can always complete the first task - the outcome would be either 'feasible' or 'not feasible'. The second one is a conditional task that kicks in only if the task is 'feasible'.

1
  • I like this concept of a "conditional task".
    – Him
    Commented Feb 29, 2020 at 16:18
0

You can apply the logic from Scrum framework under Agile where the task is either complete or not complete - there is no other state for the task. This means any partially completed tasks are considered incomplete, no matter how much the work done on the task.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.