I am struggling to get all the PMI EVM terminology sorted out. The last key for me was planned value (PV).
Let say I have a task and my BAC is $100,000 and scheduled for 4 weeks.
2 weeks in I am done 40% of the work and spent $50,000. So:
- PV: $50,000
- EV: $40,000
- AC: $50,000
- CPI: 0.9 (over budget)
- SPI: 0.9 (behind schedule)
6 weeks out I am done 90% of the work and spent $105,000. So:
- PV: $100,000 (according to the original baseline schedule 4 weeks should have got me $100,000 of EV)
- EV: $90,000
- AC: $105,000
- CPI: 0.86 (more over budget)
- SPI: 0.9 (still behind schedule)
7 weeks out I am done 100% of the work and spent $112,000. So:
- PV: $100,000 (according to the original baseline schedule 4 weeks should have got me $100,000 of EV)
- EV: $100,000
- AC: $112,000
- CPI: 0.90 (over budget)
- SPI: 1.00 (always 1 when complete)
My questions (have I explained / understood this correctly?):
- As soon as you are past your original budgeted timeline for a task your PV = BAC
- PV is the cost you should have accrued if your original schedule was correct (for the same time frame)