I have a User Story that contains a bunch of tasks, similar to this:
User Story: Fix any broken JavaScript in CMS
- Task: Find and fix broken JavaScript in content
- Task: Find and fix broken JavaScript in code base
- Task: Find and fix broken JavaScript in static files
- Task: Find and fix broken JavaScript in library
- Task: Find and fix broken JavaScript in catalog files
So I have a bunch of tasks to go through some code and files and fix some JavaScript. Let's say that all of the above tasks cannot be completed by me in a 2 week sprint.
How do I split this up into multiple stories? The tasks can be completed in any order and are not dependent on each other at all. So there is no logical way to sub-group them. Would I just do:
User Story: Fix any broken JavaScript in CMS (part 1)
and
User Story: Fix any broken JavaScript in CMS (part 2)
That seems like a poor way to manage this. What is a better approach to this kind of problem where tasks can't be grouped any better but you still need to split the story up?