I have a project that has many tasks, some of them needs others as requirements, others don't. All tasks have a duration that will not change. We have 5 "workers" that can work at only one task at a time.
Is it possible to find the best possible way to assign tasks to reduce total time?
I've tried OmniPlan but I'm not really a project manager and don't know how the software works.
I've managed to assign some tasks to a worker and "level" them to see one before the other. But I have to manually assign a task to a worker and I have a lot of tasks.
Is there any software that can calculate that?
Example:
Task 1 - 1d
Task 2 - 3d
Task 3 - 3d
Task 4 - 7d
Task 5 - 9d
Task 6 - 2d
Task 7 - 5d
Task 8 - 3d
Possible Distribution:
Worker 1: Task 5
Worker 2: Task 4, 6
Worker 3: Task 2, 3
Worker 4: Task 1, 7
Worker 5: Task 8