2

Is it possible to omit some tasks from being used in the calculation of a resources allocation percent.

I've looked at this a number of different ways but in short, I want to have a couple of tasks running in parallel that are assigned to one resource. However, I know that for this set of tasks, I want to calculate the resources allocation for only one task. To do this I'd like to remove the task from the resource allocation calculation.

I know I can do percentages but when the number of tasks goes up and down I don't want to have to change them as that task number changes.

Question
Is it possible to enter a task, the expected duration, assign one or more resources and on a one by one basis omit them from the resource allocation calculation.

2 Answers 2

1

I'm afraid not. You could swap resources with a resource that you set a large number of max units to avoid overallocation. But the peak units are calculated based upon assignments to all tasks - you cannot omit some.

0

I found something that was between a solution and a hack but it works for me.

This works well in the scenario below but is not guaranteed for other scenarios.

Summary Task
- [Time Block]: 10D
- Sub Task 1: 5D
- Sub Task 2: 5D
- Sub Task 3: 5D
- Sub Task 4: 5D

I'm comfortable with saying the summary task will take 10 days but I'm not comfortable with allocating time on a sub task basis. So I:
- Assign the resource to the Time Block task at 100%
- Assign the same resource to the sub tasks at 0%
- Ensure that the task type is "Fixed Duration"

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.