In a drawing activity diagram when it says:
Activity A Follows Activity B
does it mean A->B
or B->A
?
I am confused with this lingo.
Due to your post in PMSE, I assume you are taking about network diagrams (vs. SW-engineering activity diagrams)? For network diagrams, it's like in normal language usage:
See http://en.m.wikipedia.org/wiki/Dependency_%28project_management%29