I have a Microsoft Project 2013 schedule where I would like to have an overall task that takes 100hrs from 3 resources. ResourceA and ResourceB will be fully loaded for 90% of that time. ResourceC is there for support and I only expect him to be used for 10% of effort spread, but used for the full duration of the task.
|--------------TASK---------------| 100 hr, 5.6d;
|-------TASK Implementation-------| 90 hr, 5.6; ResourceA[100%], ResourceB[100%]
|-------TASK Support/Review-------| 10 hr, 5.6d; ResourceC[???%]
| Task Name | Work | duration | Resource Name |
| TASK | 100 hrs | 5.6d | |
| TASK Implementation | 90 hrs | 5.6d | ResourceA, ResourceB |
| TASK Suuport/Review | 10 hrs | 6.6d | ResouceC [???%] |
Creating the task for ResourceA and ResourceB is straightforward. But, how do I create a task for ResourceC where it is fixed to the start and stop of the other task and the loading of ResourceC is variable?