Is it acceptable to swap out stories from the current sprint to the backlog and replace them with stories of the same estimate size from the backlog, because of changing priorities in the business?
My opinion/experience tells me that this is an absolute no-no and that if the business needs to change, let's say, 70% of the work in the current sprint then we should abort the sprint early and start a new one - with a new commitment.