I am working on MS Project 2013. The summary task No. 6 is not showing the duration correctly. Refer to the picture below.

enter image description here

Please help.

1
  • Welcome to PMSE. Due to link decay and blockers, please include sufficient information in the Question itself in order to allow an answer. That is, explain in words what the problem is (or include the picture directly in the Question as an attachment, not a link).
    – Sarov
    Commented Sep 20, 2018 at 14:03

1 Answer 1

2

Summary task 6, Building Town planning, contains three unlinked subtasks of durations 200d, 300d, and 476d - all of which start concurrently. The duration of the summary task, at 476d, is exactly as expected - i.e. the difference between its start and finish dates according to the applicable calendar. Summary start and finish dates are rolled up from the subtasks. Since all the subtasks start at the same time, the summary's finish date and duration are both determined by the longest subtask - 476d.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.