0

I'm working on creating a burndown graph for a large project that I'm trying to schedule, but I don't want the sub-tasks to be counted as a remaining actual task for the burndowns. Is there a method to mark tasks as 'non-countable' or something for this field?

Thanks!

1 Answer 1

1

I may have found a work around for my issue, in the post here

There is a tip at the bottom claiming: "assigned actual work that is equal to the Work field." This seems to fix things from a reporting stand point on the task usage screen and the burn-down graph. I have to test to see if it marks the task 100% complete though, which is not what I want to do.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.