0

I'm working on creating a burndown graph for a large project that I'm trying to schedule, but I don't want the sub-tasks to be counted as a remaining actual task for the burndowns. Is there a method to mark tasks as 'non-countable' or something for this field?

Thanks!

1

I may have found a work around for my issue, in the post here

There is a tip at the bottom claiming: "assigned actual work that is equal to the Work field." This seems to fix things from a reporting stand point on the task usage screen and the burn-down graph. I have to test to see if it marks the task 100% complete though, which is not what I want to do.

| improve this answer | |