These are my default calendar options:
- Default start time: 8am
- Default end time: 5pm
- Hours per day: 8
- Hours per week: 40
I have two resources. Resource 1 has the standard calendar (8 hours / day) as base calendar, and Resource 2 has Calendar 1 as base calendar.
Calendar 1 has 9 hours/day. Working times: Mon - Fri 8am - 12pm, 1pm-6pm
I created two tasks. Resource 1 is assigned to Task 1, and Resource 2 is assigned to Task 2. I then entered the start and finish times for both tasks (13/7/15 - 16/7/15 for both tasks).
When I went to the Resource Usage page, Resource 1 is working 8h for all the four days of the task. Resource 2 is working 9h for the first three days, and 8h for the last day.
- Why is Resource 2 only working 8 hours on the last day?
- Why is it not 9 hours for each day that he is working and what can I do so that he is automatically working 9 hours for every day?
- When I manually change the last day so that he is working 9 hours, why does it turn red?
This happens whenever I assign a resource that does not have the Standard Calendar as the base calendar. The last day will have a different number of hours. What can I do to fix this?