yesterday I was trying to put in my resource sheet a part-time worker. I changed his calendar appropriately and then assigned him.
At that point something strange happened.
I summarized everything in this screenshot from an example project I made for the occasion:
As you can see in the second frame, I changed my calendar to a 8.00 to 12.00 part-time range. 4 hours per day, Monday to Friday.
In the first frame, two ackward things happened:
the duration is calculated like if the resource's calendar is a Standard 8 hours per day (Task 1&3 - 4 hours result in 0,5 days instead of 1; Task 2 - 8 hours result in 1 day instead of 2)
no overallocation is detected between Task 1 and Task 2
What am I missing?
Thank you all for your support,
Oliver