Hopefully you can help provide me with insight.
So I'm new to the Agile functions of MS Project, and I have a board with sprints and tasks set up. When inspecting the dates for Start/Finish times of these tasks, the dates are all incorrect; for example, if I move a task from To Do to Complete on the Sprint Board view, see it marked as complete, and check the Task Sheet, the date says 8/5 (start of the Project Date) despite today being 8/8 and the task being created today (which shows the correct date). No matter what task or sprint I mark as complete, the date always shows the Project Start date instead of the date its being modified on. I've checked Project Information and Today's Date is set appropriately at 8/8, so I don't think that's the problem.
What am I missing?
Thanks in advance for your help!