I have task B which cant start until task A is finished (FS) but must end with task C end date (FF)(i.e. duration of B might be floating depending on the end of task A and end of task C) .. is this achievable on msproject?

1 Answer 1

1

It sounds like you may need a "Hammock" task, which is something that I asked about some time ago on this site. The original question (and associated answers) are here: In MS Project, can I create a task whose duration depends on two milestones? .