Once I've set up my baseline, I like to use the Tracking view to see schedule slippage (ie: is a project going to be "late"?). The problem occurs when I'm updating the % Complete, but a task that was supposed to be complete (or in progress) has not been started yet, so I leave it at 0% Complete. Project doesn't update the tracking Gantt, so you can't see that the project is "slipping".
How do you handle this?
My "Hack" Workaround
In my Options > Calculation I generally have the following set:
- Move end of completed parts after status date back to status date.
- Move start of remaining parts back to status date.
- Move start of remaining parts before status date forward to status date.
- Edits to total task % complete will be spread to the status date.
For tasks that are complete or partially complete, this works great - just fill in the % Complete value, and things jump around, showing you if you're ahead or behind schedule for the remaining tasks.
However, if a task that was supposed to start before the current status date has not even started, I don't know how to make Project push that task forward to the current status date. The only workaround I've found is to assign it a small % complete, such as 1%. Then it moves the remaining part of the task forward to the status date. But this seems kind of hackish to me.
How can I get MS Project 2003 to show schedule slippage on unstarted tasks? Is there a setting / Tool or other feature I need to be using?
Example
Set up a new Project with the following tasks: 1. Task 1 (1d) starts on Monday 2. Task 2 (2d, dependent on 1) starts on Tuesday 3. Task 3 (1d, dependent on 2) starts on Thursday 4. Task 4 (0h, milestone, dependent on 3) Finishes on Friday.
Now, let's set the Status Date to Thursday - we're updating the project plan.
In Scenario 1, Task 1 is 100% complete, but task 2 for some reason is only 50% complete. If we fill that information in, Project will split task 2, and move the second part of the split (the remaining 50%) to start on Thursday. As a result, Thursday's task moves to Friday, and our Friday milestone moves to Monday and we can clearly see the project completion will be late by a day (1 day's slippage).
In Scenario 2, Task 1 is still 100% compete, but task 2 hasn't been started yet (0%). If we fill in the 100% complete for Task 1, and leave everything else at 0%, Project does NOT move Task 2 to Thursday, and as a result there doesn't appear to be any slippage, so at a glance we might conclude the project is still on-time. As a workaround, if I put a 1% in for Task 2, then it does go ahead and splits the task, but that's just a hack to get it to update the timeline, and can't be the only way to do things. At least I hope not. Hence this SE question!