2

I need to add a task to my WBS/Gantt Chart in MS Project, but not number it as it is a task (Kickoff meeting) that I want to fall under the heading: Project Administration. I need this to be a general task that is not part of the Project WBS I have created but somehow still show up on it as a general item.

How can I do this?

1
  • Is your project structured as a flat WBS where all tasks are at the same level, or do you indent tasks beneath others to form headings / groups? Have you considered whether you could simply include this as a lower level (indented) task within a higher level "Project Administration" group, and simply collapse the group so that everything in it shows up under the ingle "Project Administration" rolled up task?
    – Iain9688
    Commented Dec 1, 2015 at 19:22

2 Answers 2

1

I'm afraid the WBS or Outline numbers will automatically number the task. You can use a spare text field (text1) to set up your own WBS codes and simply skip adding one to the task in question.

1

If you have generated a WBS in the WBS field of MS Project, all tasks/lines will be numbered. If I need to get around this by not adding tasks to the overall project WBS, then I have a section at the top of my schedule where I put Program Milestones that are linked to my program schedule below. This way I can add as many milestones as I need and will not change the overall structure of the agreed upon program schedule. It seems to give me some flexibility. Example:

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.