0

Probably a noddy question, but need to ask. I'd like to be able to demonstrate real time slippage on my plan, for remodeling impact purposes. I have both original baseline dates and current dates added to my plan. Is there a way of linking these to show a separate column with real time, total days slippage

2 Answers 2

1

In the ribbon, open the "Baseline" drop-down menu and click on Baseline. You will be able to make visual comparisons--for each task--between the Gantt bars for the current plan versus the baseline.

0

Open up your Finish Variance column. It calculates gap between Finish Date and Baseline Finish Date.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.