I have a MS Project 2007 plan with six months of work in it. I'm updating the % Work Complete on the tasks as we progress through the plan each week and month.
I'm moving the "Project Start" date each day I work on the project so that it re-levels the tasks based on the current date and I can tell when my projected release date will be.
What frustrates me is completed tasks remain to the right of my "Project Start Date" line. It seems like auto-leveling should move the completed work to the left of the "Project Start Date" line, correct? How do I make Project behave like I want?
I could be using MS Project totally wrong. Maybe I need to change my workflow a bit.