When I create a new task in Microsoft Project it defaults to "Fixed Units", however most of the projects we do are estimated upfront so we need to schedule based on fixed amount of effort but variable amount of resources, i.e. we can add more resources to meet a deadline.
At the moment, I have to go in and change the tasks to be "Fixed Work" by selecting all tasks and editing them in the Advanced menu.
Is there a way this can be set as the default?
Thanks Marko