I've recently made the move to Project 2013 Standard (15.0.4727.1001) and seem to be having problems using even simple filters I've created within custom reports. For example, I wanted to create a simple "show all tasks which are past their finish date" report. Starting simple, I created a filter with one criterion:
"<%Complete> <is not equal to> <100%>"
The report returns only a handful of tasks (mostly summary tasks, if that's any clue) - but many fewer than meet this criterion. This occurs regardless of the Outline Level I select.
This seems so straight-forward I must be missing something - or is this functionality just that weak?
Update: It appears that some of the predefined filters aren't being respected, either. For example, my report only shows one task with the "In Progress" filter applied and only a handful when the "Incomplete Tasks" filter is applied - both clearly wrong.