I am currently running a project to develop about 50 parts. Each part has about 100 actions from engineering to production to shipping. I created one standard project file for a standard part. Then I reviewed each part against the standard to make changes only to the non standard actions.
Now I have 50 separate projects that pull from the same resource pool. When I insert them all into a master project, MS project crashes more than half the time. Most likely I do not have the processing power to have 50 projects linked together.
When I copy and paste each set of actions into one project, I have to manually change all the predecessors as the line numbers change but the predecessors don't. Is there a way to copy and paste tasks from one project file to the other without loosing the predecessors?