-1

I had set a baseline previously and I am now updating to show what has actually happened. I went into the task information and changed the "start" and "finish" dates to what actually happened. When I hit ok MS Project then changes the "actual duration" to 0 days... even though it should be 7 days. Any ideas why this happens?

enter image description here

3
  • I cannot reproduce this behaviour in MS-Project 2013. Can you provide exact repeatable steps and also specify the MS-Project version you are using (in a tag)?
    – Marv Mills
    Commented Jun 20, 2016 at 13:04
  • I'm using MS Project 2010. The steps in the original question are as exact and repeatable as I can think of. Commented Jun 21, 2016 at 17:24
  • 1
    I think it had something to do with trying to set an actual finish date that is earlier than a predecessor's scheduled finish date. I removed the predecessor and then the problem stopped. Slightly frustrating because I then loose traceability to the baseline dependency relationships. Thank you for trying to look in to this Marv Mills Commented Jun 21, 2016 at 17:30

1 Answer 1

1

Display the remaining duration field. Open Task Information, go to the advanced tab. Uncheck the box for "mark as milestone".

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.