When I'm editing start or finish dates, Project moves the other based on the duration. How do I make it change the duration instead so I don't have to keep moving the start and finish dates back?
Thank you
You should never / rarely hard code a date in. Open up the duration column and enter a new duration there. Then let your schedule logic calculate the start and finish dates based on your schedule network.