New to MS Project Macro, but use to writing some level of macros in excel.
I want to write macros that apply different logic only on the predecessors of the activity or selected activities.
e.g filter only selected task and its predecessors Or find the predecessors and see which ones have been completed.
The questions is, how do I read the processors? Do I read them as a text strings and then separate them based on commas OR there is a way to define a predecessor variable / variables and then apply a filter based on task ID?