1

In MS Project 2016, I have a resource: call them Foo. They are assigned hours in many tasks. They must work:

  • Task A: 20 hours
  • Task B: 40 hours
  • ...
  • Task Z: 30 hours

Foo quit the company, and we hired a replacement, Bar. Bar is hired to do exactly Foo's old job.

Question: How can I, in one operation, replace Bar as the resource for every task Foo was previously assigned?

I have seen many answers to select the task in question, click "assign resources", then select the resource and hit replace. This only works if I manually click every one of the correct tasks from A to Z.

1 Answer 1

1

I would tackle this problem manually as I have no knowledge of a technical solution in MS Project. I would filter out tasks that have actual data loaded--any tasks that have finished or are in progress--leaving only those tasks that have not started. I would copy and paste into excel the resources data and then make a global change to remove the exited employee and replace him with the new employee. Then I would copy and paste those data into MS Project. Then I would load cost information for that new employee in the resource table. I would NOT rebaseline the new tasks, however, because changing employees is typically insufficient to justify a rebaseline.

Moving forward, I would NOT use specific employee names in the scheduling tool to avoid this type of nuisance change. I use roles or labor categories in my schedules. Therefore, changing, adding, or removing employees on the project will necessitate no change in the tool.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.