In MS Project 2016, I have a resource: call them Foo. They are assigned hours in many tasks. They must work:
- Task A: 20 hours
- Task B: 40 hours
- ...
- Task Z: 30 hours
Foo quit the company, and we hired a replacement, Bar. Bar is hired to do exactly Foo's old job.
Question: How can I, in one operation, replace Bar as the resource for every task Foo was previously assigned?
I have seen many answers to select the task in question, click "assign resources", then select the resource and hit replace. This only works if I manually click every one of the correct tasks from A to Z.