Skip to main content
2 votes

What is the difference between "status report" and "variance report"?

Well for starters - baseline(s) could be anything - cost, schedule etc but perfomrance measurement baseline is a subset of all the baselines. Secondly, status report, as said is focused on vitals of ...
Manish Adhikari's user avatar
2 votes

Is there a report type to document a (Agile) project journey?

You might be looking for a Project Charter. This kind of documents varies a lot from project to project. With regards to tools and techniques, I share a part of the linked article. The Agile ...
Tiago Cardoso's user avatar
1 vote

Ideal approach to visualise cost replacement migrating from vendor A to B

Kind of like a quasi-burn down to burn up chart? You can achieve that by a stacked column chart, like this: Here is the JSFiddle if you want to play with it https://jsfiddle.net/y4djftv9/4/
Bogdan's user avatar
  • 15.5k
1 vote

How to track progress for non functional activities

TL;DR Classifying testing or security as non-functional requirements may or may not be appropriate for your project. Regardless, all work related to a project's expected outcomes can and should be ...
Todd A. Jacobs's user avatar
  • 50.7k
1 vote

What is the difference between "status report" and "variance report"?

I cannot speak to what Rita Mulchahy's definitions are but the PMBoK does not contain a definition of Variance Report in any way. It does discuss variance analyses as a technique to determine where ...
David Espina's user avatar
  • 37.2k
1 vote

Actual Duration Calculated by MS Project vs Actual Duration of the Project as of the Status Date

The “Actual Duration” of an in-progress summary task (including a project summary task) in MSP is NOT the same as – nor even closely related to – the elapsed work days from the start of the summary to ...
Tom Boyle's user avatar
  • 1,051
1 vote

Actual Duration Calculated by MS Project vs Actual Duration of the Project as of the Status Date

I think the simple answer is that you have a mismatch between the calendar you are using to manually calculate duration and the standard calendar MSProject is using to calculate it. You need to build ...
David Espina's user avatar
  • 37.2k
1 vote

Is there a report type to document a (Agile) project journey?

We conduct risk assessments during our projects. The resulting risk register enables us to share evaluations of our improvement and tells our team's story of changing and adapting.
userden's user avatar
  • 111

Only top scored, non community-wiki answers of a minimum length are eligible