I currently add header and footer via File > Print > Page Setup, then tabs "Header" and "Footer".
It seems these header and footer settings differ, however, by the view selected. For example, if I select view "Tracking Gantt", I see the header and footer I added, but if I select view "Task Sheet", I see the default header and footer.
Does Microsoft Project allow specifying a default header and footer, for all views?
Note: I hope to upgrade soon, from Microsoft Project Standard 2010, to Microsoft Project Professional 2013 or 2016, so any notes on whether those support this functionality would also be appreciated.