I'm stuck with an issue with scheduling my construction project.
A concrete slab pour takes only one day to complete and we pour two floors a week, every Tuesday and Saturday (3-day schedule). I set up Saturday as a workday in the settings already.
The 26th Floor is the first date (5/3/17) which I inputted manually because I need the rest of the floors to auto schedule from each other.
In the example below, please help me figure out what my formula should be in the predecessors column and if I need any constraints.
The first error as you can see below is on the 30th floor slab pour. The finish date needs to say "Say 5/13/17".