How do I make MS Project (2010) distinguish between different kinds of dependencies? For example, consider the following two kinds:
Some tasks I mark as dependent on other tasks due to the nature of the tasks themselves (to use a concrete example: if you're building a house, the task to lay the foundation must come before any of the the tasks to put in the windowframes).
Other tasks I mark as dependent on each other due to resource constraints (e.g. the task to put in the living-room windows comes before the task to put in the kitchen windows, but only because I have a single carpenter. If I had two carpenters, the work could happen in parallel.