I have successfully implemented fixed costs for a few of my tasks, one of them being accommodation cost which is a "one off" cost. However, how do I input fixed costs for tasks which rely on the duration?
For example, one of my tasks involves renting special machinery for 2 days (which is my duration), the cost of renting this equipment is £13,500 per day. So how do I work out the cost, baring in mind that 2 days is the estimated period, in best case scenario the task may take one day,in worst case scenario it may take four days.
So how do I input renting costs? do I just calculate them based on the duration so £13,500 x 2 (days) .. making the fixed cost of £27,000?