I have a project with a slew of tasks. Let's say for the sake of example I have 5 tasks and these 5 tasks will take 5 calendar days to execute. But, due to the nature of the task, a resource can only work 2 hours a day on the task due to the nature of the task.
Is there a way to create a task in project such that is has a duration, but does not fully impact the resource over that duration?