I am creating and updating an integrated multi-project/vedor MS Project task tracker with the sole purpose of finding date issues, dependency issues, etc., so that we can align vendors in future meetings.
However, whenever I connect tasks (add predecessors) if there is an issue with the dates, instead of just highlighting them, they change them to "fix" the issue, which completely rendors this MASSIVE integrated task tracker pointless.
I don't want it to auto-change/fix ANYTHING! I'd rather it red them, highlight them, or literally do nothing, as we should be able to see late, past, overlapping tasks in a report.
I have to CONSTANTLY go back and change dates so they are correct for that particular vendors plan. It's honestly Beyond frustrating. I have literally unchecked EVERY box in the schedule area and it still does it. I would NOT use MSP for this if I had a choice, but I don't. I'm just a guppy in this pond.
PLEASE HELP before I lose my mind. How do I turn this auto correct for dates off?????