Curious if there is a way to avoid Microsoft Project auto-adjusting the assignment units, when I add a resource in the Resource name column.
In the project settings all resources are set to 100% availability and all tasks are set to fixed units.
Basically, I'd like to have a resource always enter with 100% assignment, even for tasks that are less than 8hrs, as it currently auto-adjusts the assignment based on the percentage of the workday, that the work estimate is - see below example.
I can manually adjust the assignment back to 100%, but for huge projects, this is really annoying.
Is there any way to override this?