What is the best approach for having contract start and end dates in MS Project?
The issue I am facing is the following: I entered both dates as milestones. all project activities are of course between those two dates. The issue is that for example the tool cannot calculate and show critical path correctly because it "thinks" the project starts from the contract start date and ends on contract end date. I also tried defining deadlines, but I noticed the same effect.
What is the best practice for tracking contract start and end dates and does it even make sense?