Linked Questions
10 questions linked to/from How should we plan work on support issues without a "battery"?
18
votes
4
answers
5k
views
How to deal with hotfixes keeping the scrum methodology
My team works with scrum methodology.
However, during some sprints we have hotfixes that have to be developed as soon as possible, so we treat them in the current sprint, and consequently we have an ...
1
vote
4
answers
9k
views
What is the specific Custom Fields Formula using (GREEN, YELLOW and RED) indicators for Task Start and Finish Dates?
What is the specific Custom Fields Formula using (GREEN, YELLOW and RED) indicators for Task Start and End Dates as follows in MS Project?
1 Task Start Date is within 5 or more of the Task Start Date ...
26
votes
1
answer
694
views
What is a “battery”?
I was very surprised to read, in this question, the mention of “batteries” as a PM tool, seemingly linked to Scrum. The OP talks about an article about their use, but none of my desperate Googling ...
2
votes
4
answers
647
views
Ticket must be worked immediately, and definitely won't make it to Done by end of sprint
It's the second to last day of sprint. Something comes in from the field that is critical. It will take approximately 2 days to complete. It will not be complete by end of sprint. Other items that are ...
3
votes
4
answers
784
views
Who decides if something should NOT be injected into a Sprint?
On some teams, I've seen it be a combination of operations and Product Management stating that either new/missed requirements came in, or bugs are severe enough to warrant injection. The Scrum Team ...
1
vote
3
answers
2k
views
How can I manage both user stories and other non-backlog tasks if using VersionOne?
We are taking our first steps in agile and Scrum. We use VersionOne for managing our user stories and tasks.
As the development manager, I am trying to build a sprint plan for the development team. ...
2
votes
3
answers
288
views
How do you plan for Production Support in velocity-based sprint planning
In capacity-based sprint planning, a calculation can be performed in order to build in production support hours by having one developer's capacity minimized.
How would a team plan for production ...
1
vote
4
answers
412
views
Sprint Bouncer role
Our engineering team uses agile scrum and we are finally growing enough to be able to delegate more scrum roles to more members, including to some of the engineers like myself.
One role we're ...
2
votes
3
answers
153
views
How should we capture "non-implementation" work?
Currently we don't capture non-implementation stories and treat any research, analysis, release, and support work as team overhead. This makes it very difficult to predict team velocity.
What is the ...
1
vote
2
answers
83
views
Planning a release around the Apple's AppStore in mind
I am currently working for a company that has adopted scrum and we are trying to figure a rule for how to account for tech support, bug fixing and the unknowns of the Apple appstore within our sprints....