1

I need to create multiple pools of resources (each containing interchangeable resources within). To clarify I need a pool of front-end developers, another of back-end developers, and a pool of testers. Each pool has temporary contractors that come and go from the project at different dates. Then, for example, I will have some Tasks that assigned to front-end only, whilst other as a mix of front-end and back-end.

I Googled this issue without luck. Any help would be welcome!

3
  • Usually a 'resource pool' is created to share the same resource among multiple files. Is that your intention? Same people, shared across multiple projects?
    – JulieS
    Nov 28, 2016 at 21:39
  • Nope. My intention is to have a group of equivalent resources assigned to a task and I would like MSP to assign the first free one to complete the task.
    – Pomario
    Dec 4, 2016 at 19:07
  • I am afraid you are destined for disappointment. :-) Microsoft project will never assign resources. You can use resource leveling to reschedule tasks when an assigned resource is available
    – JulieS
    Dec 5, 2016 at 20:41

1 Answer 1

-1

Try create a resource with its own calendar and a max capacity of 400%, 500% or whatever.

This is the way several pools of resources work in Project. For example, you can make a resource called "Testers", value 500% for 5 testers. Then, you can assign your task to that pool.

A pool of resources is when all resources in a pool have the same calendar and the same cost. If not, you don't have a pool, because you have a differente restriction in your project for each member. You need a cost and time baseline.

2
  • How does that solve the problem?
    – Pomario
    Nov 25, 2016 at 13:29
  • I'll explain better. Nov 25, 2016 at 14:17

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.